Contractor Pay Application Form G702/703 (AIA Form)

Contractor Pay Application G702/703

Overview

There is a G702/703 Contractor Pay Application form preloaded in the system.  It will pull information from the job such as Contract Totals, Retention, etc.  It can also pull forward a Schedule of Values (SOV) if you have created one in the Bundles area.   Once a Pay App has been populated, subsequent pay apps will carry forward the totals of the previous forms for a cumulative balance and percentages of completion.

Contractor Pay Application G702/703


If you have trouble viewing this video, click HERE.

G702/703 Steps
  1. In a Sale, Bundle the job lines to create a Schedule of Values.
  2. From the Sale, Transfer to Invoice Project (JR) or Invoice Custom (FM) to create this month's progress billing.
  3. Rebuild the Bundle on the Invoice screen.
  4. In the Sale, click the Forms tab and "New" > G702/703.
  5. Scroll down to the G703 > Column E  and fill in the Invoiced Bundled values for "This Period" pay application.
  6. Next month/progress billing cycle, repeat Steps 2 through 5 until 100% is met on each SOV.

Final Billing for Retention

Once the project has been invoiced in full, the last Contractor Pay Application and associated AR Invoice will be the Retention balance remaining.


If you have trouble viewing this video, click HERE.

      AR Invoice
  1. From the Sale, Transfer to Invoice Project (JR) or Invoice Custom (FM) to create the AR billing for Retention owed.
  2. Select the "Invoice Retention" toggle and generate AR invoice
      Pay Application Form for Retention
  1. In the Sale, click the Forms tab and "New" > G702/703.
  2. Copy the Retention Amount remaining on the G703.
  3. Clear the Retention value / withholding field (5a) on the G702.
  4. Paste the Retention Amount in the Balance Due field (9) on the G702.

G703  Bundled Lines Versus Entry Lines

By default, the system will fill in the G703 Schedule of Values with the Bundled SOV totals.   Now there is a new button on the G703 above Column B to enable you to populate the G703 with the "Entry Lines" from the job.   Disregarding any Bundles (and eliminating the need to bundle), the system will carry over each line from the job and its extended total sell price to the G703 form.  (Caution: if your Project has 50 lines, now the Pay Application will have 50 lines.  There are only two options: Bundled or Entry Lines, no combination. )


Training--20220822CR-KB





Was this article helpful?
0 out of 0 found this helpful